In #Singapore, the Land #Transport Authority (LTA) will open Circle Line Stage 6 (CCL6), the Downtown Line 3 extension and Thomson-East Coast Line Stage 5 this year. CCL6, linking HarbourFront and Marina Bay, is due to open mid-year, with three more stations on TEL5 and DTL3e in the second half. The additions support the Land Transport Master Plan 2040 goal of eight in 10 households within a 10-minute walk of a station by the 2030s.
On the Jurong Region Line, a new Tengah station, JS2A, will open in the mid-2030s, bringing the total to 25. Stage 1 will be delayed by six months to mid-2028 due to complex works, despite efforts to recover pandemic setbacks. Interim shuttle buses will start in late 2027.
The Cross Island Line Phase 1 is on track for 2030, with Phase 2 and the Punggol Extension due in 2032. Phase 3 works begin next year. Studies for the Seletar Line, Tengah Line and a West Coast extension will start this year.
https://www.lta.gov.sg/content/ltagov/en/newsroom/2026/3/news-releases/next-phase-of-rail-development.html